Little update.
Over the past two weeks, more progress has been made. The last two structures and pipe have been installed, underground electric has been marked by the power company, 1,000' of conduit along with a temporary power pole have been ordered, a second septic permit has been paid for, all the dirt has been moved, and the home site footprint has been cleared. I think we another 1.5-2' of cut remaining, then assess how many loads of fill dirt I'll have to buy. I'm hoping minimal, but it's not looking that way.
Steph met with our architect yesterday to get the initial changes made to our house plans. Those should be completed in the next couple weeks. I still have to draw up the detached garage so she can get plans worked up for that.
Earlier this week, I had a surprise visit from Chris
@iamdub. It was really nice to finally hang out after all these years.
Tuesday, he stopped by and we made a site visit to the property. The guys had installed the last structure and laid the downstream pipe to the headwall. They also installed the one at the bottom of the hill. I forgot to take a picture.
Chris eyeballing the pipe to structure elevation. Structure is stacked at 11' here.
Steph and I went out there today to see what they have done since then. They have the catch basin, albeit stacked out at least one riser too tall, based off an eyeball assessment. That's easily corrected and likely just stacked out to get it out of the way.
The back filling has started and is looking good. This area will be filled in and leveled over to the tree line (to the left), for the detached garage. Compacted fill material over to the catch basin, the mountain of topsoil will be wasted/stockpiled on the other side.
Random shots of the site
I flew the drone and made two quick videos. Not great, but it'll have to do.